Friday, September 26, 2008

Lake Hartwell Dream Home - Roof system framed

What a difference a week makes! The roof structure has been framed and should be decked by the end of the week. The house should be dried in early next week. The pitch of this roof gives this home a very high-end look. The interior common areas are large and spacious. Shoot me an email if you would like to drop by.

Tom Miller
tmiller@atlanta-hartwell.com




Thursday, September 18, 2008

Lake Hartwell Dream Home - Main level framing

These pictures are from last weekend. Sorry for the slow post. The basement has been framed and the main level framing has begun. This is the fun part of the project where a lake lot turns into a house very quickly.

Tom Miller
tmiller@atlanta-hartwell.com



Tuesday, September 9, 2008

Lake Hartwell Dream Home - Hammers and nails

No more concrete for a while. The lumber and the framers have arrived and have already framed out the basement level. The first two walls on the main level were erected today. This is the fun part. This should look like a house in a week or so, weather permitting.

Tom Miller